Apokoronas rallies Chania municipalities to protect the White Mountains
A plan to build eight wind turbines in the mountains above Asi Gonia has prompted Apokoronas to launch one of the most ambitious inter-municipal campaigns the Chania region has seen in years. The Municipal Council voted unanimously in an emergency session to oppose the project — and Mayor Charalampos Koukianakis has now written to every mayor and council president in the Chania regional unit, asking them to do the same.
What is planned — and what it would mean on the ground
The proposed wind farm would have a total capacity of 52.8 MW, made up of eight turbines each generating 6.6 MW. Each turbine would stand 185 metres tall, with rotor blades spanning 155 metres in diameter. To build and service the site, approximately 6.5 kilometres of new roads would be cut through the mountain terrain, and a further 8.5 kilometres of existing tracks would be widened — with particularly heavy earthworks required at bends and turns.
Mayor Koukianakis argues these are not minor inconveniences. The combination of turbine construction and road works would permanently alter the mountain landscape, damage a fragile natural environment, and inflict changes that cannot be undone. The areas at stake — Asi Gonia, the Azilaka forest, the broader White Mountains, and the countryside around Lake Kournas — hold deep ecological, historical, and cultural significance for the entire region.
The mayor also stresses that the wind farm cannot be assessed in isolation. A high-voltage power line connecting Chania to Damasta is also planned for the same general area. Taken together, the cumulative impact of both projects needs thorough evaluation before any approvals are granted.
What Apokoronas is asking other municipalities to do
Koukianakis has sent formal letters to the mayors and council presidents of every municipality in the Chania regional unit. He is asking them to put the issue on their council agendas immediately and adopt formal resolutions by November 10, 2026. Specifically, he is requesting that each council:
- State clearly its opposition to this particular wind farm in Asi Gonia
- Call for the rejection of the project's environmental terms and the refusal of its environmental licence
- Highlight the cumulative impacts, including the road works and the planned high-voltage line
- Authorise their mayors to submit the resolutions collectively, forming a unified front with a joint memorandum and using every available administrative and legal avenue
A message that goes beyond one municipality
The underlying argument from Apokoronas is simple: the White Mountains belong to everyone in Crete, not just the residents of one municipality. "Tomorrow, our children will judge us by what we protected, not by what we promised," Mayor Koukianakis wrote. "Let us not stand by as spectators — let us unite our efforts before it is too late."
Key facts at a glance
- Deadline for supporting council resolutions: November 10, 2026
- Location: Asi Gonia, Azilaka forest, White Mountains, Lake Kournas area
- Project scale: 8 turbines × 6.6 MW = 52.8 MW total capacity; turbine height 185 m; blade diameter 155 m
- Infrastructure: ~6.5 km new roads + ~8.5 km widened existing roads