Apokoronas vs ADMIE: High-voltage power line dispute heads to Greece's top court
A legal battle over a planned high-voltage power line through the Madara mountain area is now before Greece's Council of State — the country's highest administrative court. The outcome will determine whether the route chosen by grid operator ADMIE goes ahead as planned, or whether a fresh assessment of alternatives is required.
What the dispute is about
ADMIE, the state-owned electricity transmission operator, has planned a high-voltage line that would pass through the Apokoronas area and the broader Madara zone. The municipality objects to the chosen route and has filed a formal challenge with the Council of State, arguing that the planning process failed to properly examine the consequences for the local environment, public health, landscape, social cohesion, and long-term sustainable development.
According to the municipality, the obligation to meaningfully evaluate alternative routes — both a constitutional requirement under Article 24 of the Greek constitution and a European legal obligation — has not been met.
ADMIE fights back
In response, ADMIE has filed a formal intervention in the court proceedings, defending its plans. The municipality reads this as confirmation that the operator is pressing ahead with a design that, in its view, treats the area as a technical corridor rather than a living landscape with historical, ecological, and social dimensions.
Scientific backing from the National Technical University
To support its case, the municipality enlisted the National Technical University of Athens (known in Greek as the Εθνικό Μετσόβιο Πολυτεχνείο). The first phase of a scientific study has already been submitted to the court. The municipality says the final phase — which will present data on the actual impacts of the proposed line and assess alternative routing options — is due to be completed very soon.
What is at stake for the area
The municipality identifies several areas of concern it says have been overlooked:
- Environment and landscape: the line would pass through terrain with distinctive geological and natural features
- Public health: potential effects on residents living near a high-voltage line
- Social cohesion: broader community impacts of large-scale infrastructure
- Sustainable development: long-term, potentially irreversible changes to the area
The municipality's position is that the precautionary principle demands a higher level of scrutiny for major infrastructure projects in areas like Apokoronas and the Madara, which it describes as having particular geomorphological, ecological, and social characteristics.
What happens next
The case is now in the hands of the Council of State. No date for a ruling has been announced. If the court sides with the municipality, ADMIE could be required to carry out a more thorough review and consider alternative routes. If it sides with ADMIE, the current plan would be cleared to proceed.
Note: This report is based on a press release issued by the municipality of Apokoronas. The account reflects the municipality's position; ADMIE has not made a public statement in response.