Chania–Damastas power line: NTU study calls for planning review
A final report by the National Technical University of Athens (NTU) has concluded that the planning process for the proposed high-voltage line between Chania and Damastas failed to examine key routing alternatives with adequate rigour. The municipality of Apokoronas announced the findings on May 14, 2026.
What the study found
The NTU research programme determined that underground and undersea routing options were not investigated with the thoroughness the decision required. According to the study, the potential consequences of the planned overground line are real and serious, affecting the natural environment, the agricultural sector, local villages, tourism, and the social fabric of the wider area.
The municipality of Apokoronas had opposed the original routing from the outset, arguing that alternatives had not been given proper consideration. The municipality describes the NTU findings as scientific confirmation of that position.
Public presentation — May 21, 2026
The NTU research team that produced the report will present its findings in person at a public event open to all. Residents, members of parliament, regional authorities, municipal bodies, professional associations and young people are all encouraged to attend.
- Date: May 21, 2026
- Time: 7:30 pm
- Venue: Apokoronas Municipal Council chamber, Vrysses
Background
The Chania–Damastas high-voltage line has been contested since it was first proposed. The municipality and local residents have repeatedly called for a thorough examination of underground and undersea alternatives before any final decision is made. According to the municipality, that demand was not adequately addressed in the original planning process.
The NTU report — the full findings of which will be presented at the May 21 event — now forms the basis for a renewed call on the state to reconsider the decisions already taken.
Note: This report is based on a press release issued by the Apokoronas municipality. No response from the responsible state authorities or the grid operator is included in the source.